CT Clamps and Metering Sensors
CT clamps and metering sensors must be installed per manufacturer instructions following NEC codes. Key requirements include proper orientation toward load/panel, full closure and latching, routing through low-voltage pathways only, and validation of readings in the app.
On this page
Code Reference (NEC)
- NEC 110.3(B) – Installed per manufacturer instructions
- NEC 300 – Separation of Class 2 / power conductors
- NEC 725 – Control and signaling circuits
CT Locations
- Mains CTs (required)
- PV CTs (if applicable)
- Generator CTs (if applicable)
Installation Rules
- Observe orientation arrows toward the load/panel
- Fully close and latch CTs
- Route CT leads through low-voltage pathways only
- Never extend CT wiring unless approved
Validation
- Confirm readings are correct in the app
- Check for reversed polarity or zero values