Battery System Installation Guide

Installation guide for battery systems including NEC code references, supported architectures such as Tesla Powerwall and Powerblocks, wiring procedures, and commissioning checklist.

On this page

Code Reference (NEC)

Supported Architectures

Kora interfaces on the AC side unless otherwise specified.

Key Installation Principles

Wiring and Installation Steps

  1. Install battery system per manufacturer instructions
  2. Land battery/inverter AC output at the designated breaker or input
  3. Size conductors per battery/inverter specs
  4. Install battery CTs if required
  5. Confirm neutral and grounding scheme compatibility
  6. Verify communication links where supported
  7. Configure backup priorities in app

Powerblocks-Specific Notes

Commissioning Checklist

Related articles

Commissioning