Battery System Installation Guide
Installation guide for battery systems including NEC code references, supported architectures such as Tesla Powerwall and Powerblocks, wiring procedures, and commissioning checklist.
On this page
Code Reference (NEC)
- NEC 706 – Energy Storage Systems
- NEC 705 – AC-coupled systems
- NEC 480 – Storage Batteries (as applicable)
- NEC 110 – Working clearances and ventilation
Supported Architectures
- AC-coupled batteries (Tesla Powerwall, EcoFlow, etc.)
- DC-coupled batteries via hybrid inverter (Powerblocks)
Kora interfaces on the AC side unless otherwise specified.
Key Installation Principles
- Battery systems must be listed and approved per AHJ
- Kora does not replace the inverter or battery BMS
- Backup behavior is orchestrated by Kora using circuit priorities
Wiring and Installation Steps
- Install battery system per manufacturer instructions
- Land battery/inverter AC output at the designated breaker or input
- Size conductors per battery/inverter specs
- Install battery CTs if required
- Confirm neutral and grounding scheme compatibility
- Verify communication links where supported
- Configure backup priorities in app
Powerblocks-Specific Notes
- Communication cabling required
- Daisy-chain supported (up to 4 stacks)
- Refer to Powerblocks manual for stacking limits
Commissioning Checklist
- Battery visible and reporting correctly
- Charge/discharge behavior confirmed
- Backup mode tested successfully in app