Export Limiting Setup for Utilities

Many utilities require limits on how much power a site may export. Kora enforces export limits using real-time metering and control logic.

On this page

How Export Limiting Works

• Export limits are set during system commissioning

• Kora monitors net power flow continuously

• Excess generation is curtailed, redirected to storage, or load-managed

Common Use Cases

• Net Energy Metering (NEM) constraints

• Rule 21 export caps

• Non-export or zero-export sites

Verification

• Confirm export limits are active in commissioning interface

• Measure export under high-generation conditions

• Verify limits remain enforced during outages and transitions

Important Notes

• Export limits are utility-controlled, not homeowner-adjustable

• Improper CT installation will invalidate export limiting

• Changes may require utility re-approval